Income Group | High income |
Economy Score |
---|
Question | Answer |
---|---|
Does the regulatory framework allow procuring PPPs? | Yes |
If yes, please specify the relevant regulatory framework and the year of adoption: | PPPs in Lithuania are currently mainly governed by Law No. VIII-1312 of 1999 on Investments [hereinafter "Investments La... More |
and provide a link to a government–supported website where the mentioned regulatory framework is available or provide an electronic copy of it: | http://www.ppplietuva.lt/vpsp-projektai/?lang=en https://www.e-tar.lt/portal/lt/legalAct/TAR.C54AFFAA7622/mljgfOSVqW |
Are you aware of any reforms (in the regulatory frameworks – laws, regulations, policies, etc.- or in generally followed practices) related to PPPs that: Took place in 2016, are ongoing and/or are planned to be adopted BEFORE June 1, 2017? | Yes |
Please describe: | New public procurement laws, implementing EU Public Procurement Directives 2014/24 and 2014/25, were adopted and will be... More |
Are ongoing and/or are planned to be adopted AFTER June 1, 2017? | Yes |
Please describe: | EU Directive 2014/23/EU is to be transposed into Lithuanian Concessions Law. The amendments are currently being discusse... More |
Besides national defense and other matters of national security, does the regulatory framework explicitly prohibit or restrict PPPs in any of the following sectors?: Transportation. | No |
If yes, please provide the relevant legal/regulatory provisions: | n/a |
Besides national defense and other matters of national security, does the regulatory framework explicitly prohibit or restrict PPPs in any of the following sectors?: Water and Irrigation | No |
If yes, please provide the relevant legal/regulatory provisions: | n/a |
Besides national defense and other matters of national security, does the regulatory framework explicitly prohibit or restrict PPPs in any of the following sectors?: Energy generation and distribution. | No |
If yes, please provide the relevant legal/regulatory provisions: | n/a |
Besides national defense and other matters of national security, does the regulatory framework explicitly prohibit or restrict PPPs in any of the following sectors?: Telecom | No |
If yes, please provide the relevant legal/regulatory provisions: | n/a |
Besides national defense and other matters of national security, does the regulatory framework explicitly prohibit or restrict PPPs in any of the following sectors?: Other | No |
If yes, specify and provide the relevant legal/regulatory provisions: | n/a |
Does the regulatory framework provide for a specific tax regime for PPP transactions (i.e. tax incentives, special tax depreciation treatment, etc.)? | Yes |
If yes, please specify and provide the relevant legal/regulatory provision (if any): | Article 4(1) of the Real Estate Taxation Law provides for private partners being exempt from real estate taxes. This Law... More |
Please identify the PPP procuring authorities in [country_name] and provide their website(s) (if available): | Procurement authorities are generally official entities either at the national level or the municipal that initiate the ... More |
In addition to the PPP procuring authorities listed above, is there a specialized government entity that facilitates the PPP program (PPP Unit)? | Yes |
If yes, please indicate its name, and its website (if available): | The Central Project Management Agency Centrinė (Projektų Valdymo Agentūra - CPMA), website: www.cpva.lt |
If yes, what are the main responsibilities of the PPP Unit (check all that apply): PPP regulation and policy guidance. | Yes |
PPP capacity building for other public authorities. | Yes |
PPP promotion among the public and/or private sectors in national and international forums. | Yes |
Technical support in implementing PPP projects. | Yes |
Identification and selection of PPP projects from the pipeline. | No |
Revision of fiscal risks born by the Government. | No |
Consultation with affected communities on potential impact of PPP projects. | No |
Approval of PPP projects. | Yes |
Undertaking the procurement of PPPs. | No |
Oversight of PPP implementation. | No |
Other | No |
please specify: | n/a |
Please provide the relevant legal/regulatory provisions: | n/a |
Question | Answer |
---|---|
Does the Ministry of Finance or Central Budgetary Authority approve the PPP project before launching the procurement process? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | According to Articles 23-25 of the PPP Resolution, in the case of central government PPP projects, the Ministry of Finan... More |
Does the Ministry of Finance or Central Budgetary Authority approve the PPP project before signing the PPP contract? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | The Ministry of Finance must ascertain the compliance requirements before the PPP negotiations are concluded and the awa... More |
Does the Ministry of Finance (or government more broadly) have a specific system of: Budgeting for PPP projects. | No |
If yes, please provide the relevant legal/regulatory provisions (if any): | n/a |
Accounting liabilities (explicit and implicit, direct and contingent) arising from PPPs. | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | These liabilities are considered as liabilities on the institution implementing the partnership project and Ministry of ... More |
Reporting liabilities (explicit and implicit, direct and contingent) arising from PPPs. | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | According to Article 40.3 of the PPP Resolution, the Ministry of Finance submits to the Government of the Republic of L... More |
If yes to question 8.2, which of the following alternatives best describes the regulation?: Accounting and reporting according to International Public Sector Accounting Standards (IPSAS). | No |
Accounting and reporting according to other international standard (e.g. European System of Accounts). | Yes |
Please specify: | European System of Accounts 2010, Eurostat Manual on Government Deficit and Debt |
Other. | No |
Please specify: | n/a |
Besides the procuring authority and the Ministry of Finance or Central Budgetary Authority, does any other authority(s) approve the PPP project before launching the procurement process (e.g. Cabinet, Cabinet Committee, Parliament, Supreme Audit Office, et | Yes |
If yes, please specify the relevant authority | With regards to central PPP projects, the PPP Commission, the Seimas of the Republic of Lithuania (parliament) on the re... More |
and provide the relevant legal/regulatory provisions (if any): | PPP Resolution Articles 12-17, 28-29. Investments Law Article 15.9 |
Besides the procuring authority and the Ministry of Finance or Central Budgetary Authority, does any other authority(s) approve the PPP project before signing the PPP contract? | No |
If yes, please provide the relevant legal/regulatory provisions (if any): | n/a |
Does the procuring authority use transaction advisors during the PPP project cycle? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | General provisions of the Public Procurement Law (Art.10) on hiring experts when special knowledge or assessment is requ... More |
In a case comparable to the case study assumptions, please select the option that best describes the way your government integrates the prioritization of PPP projects with other public investment project prioritization? (e.g. in the context of a national | No |
If yes, please specify and provide the relevant legal/regulatory provisions (if any): | n/a |
The regulatory framework prescribes the need for PPPs to be consistent with all other investment priorities without establishing a specific procedure to achieve that goal. | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | Article 14 of the Investments Law provides, "The state investment policy shall be formulated in the Programme of the Gov... More |
The regulatory framework does not include any provisions but the procuring authority evaluates the consistency of PPPs with other government investment priorities in practice. | No |
If yes, please elaborate: | n/a |
The procuring authority does not evaluate PPPs against existing government priorities. | No |
Please elaborate and provide examples: | n/a |
Based on your experience, is it always the case that this prioritization is done in practice in accordance with the provisions of the regulatory framework described above? | Yes |
If yes, please specify: | In practice, priority projects notably get more attention from politicians and result in faster decision making. For exa... More |
If no, please elaborate: | n/a |
Which of the following assessments are conducted when identifying and preparing a PPP in order to inform the decision to proceed with it? (check all that apply): Socio-economic analysis (cost-benefit analysis of the socio-economic impact of the PPP projec | Yes |
Relevant legal/regulatory provision (if any) | The PPP Resolution Article 6.4 refers to the Methodological Documents, approved by the CPMA, as part of the evaluation s... More |
Is there a specific methodology for the assessment? | Yes |
If yes, please elaborate | The Socio-Economic Methodology highlights the impact by PPP projects on health care, social security, and education and ... More |
Is the assessment done in practice? | Yes |
Details: | It is a mandatory part of an investment project, and CPMA does not approve projects without such analysis. |
Affordability assessment, including the identification of the required long term public commitments (explicit and implicit, direct and contingent liabilities) | Yes |
Relevant legal/regulatory provision (if any) | Art. 15 of the Investments Law provides: "2) economic and financial aspects of the general government and private entiti... More |
Is there a specific methodology for the assessment? | Yes |
If yes, please elaborate | Sections 4 & 5 under "Financial" and "Economic" Analysis of the Preparation Methodology provide the different components... More |
Is the assessment done in practice? | Yes |
Details: | It is a mandatory part of an investment project, and CPMA does not approve projects without such analysis. |
Risk identification, allocation and assessment (risk matrix) | Yes |
Relevant legal/regulatory provision (if any) | Art. 15 of the Investments Law requires a prior negotiation assessment including: 1) any risks related to activity trans... More |
Is there a specific methodology for the assessment? | Yes |
If yes, please elaborate | The Preparation Methodology provides a basis for such an assessment under "Sensitivity and Risks" in Section 6 provide t... More |
Is the assessment done in practice? | Yes |
Details: | It is a mandatory part of an investment project, and CPMA does not approve projects without such analysis. |
Comparative assessment to evaluate whether a PPP is the best option when compared to other procurement alternatives (i.e. value for money analysis, public sector comparator) | Yes |
Relevant legal/regulatory provision (if any) | Art. 15 of the Investments Law provides: "2) economic and financial aspects of the general government and private entiti... More |
Is there a specific methodology for the assessment? | Yes |
If yes, please elaborate | Section 3 on "Feasibility and Options" in the Preparation Methodology approaches comparative assessment and details its ... More |
Is the assessment done in practice? | Yes |
Details: | It is a mandatory part of an investment project, and CPMA does not approve projects without such analysis. |
Financial viability or bankability assessment | Yes |
Relevant legal/regulatory provision (if any) | Art. 24 of the PPP Resolution provides, "the Ministry of Finance evaluates the financial conditions, specified in the pr... More |
Is there a specific methodology for the assessment? | Yes |
If yes, please elaborate | CPMA Order No 2014 / 8-337 on Dec. 31, 2014 on PUBLIC AND PRIVATE PARTNERSHIP ISSUES METHODICAL RECOMMENDATIONS http://w... More |
Is the assessment done in practice? | Yes |
Details: | It is a mandatory part of an investment project, and CPMA does not approve projects without such analysis. |
Market sounding and/or assessment (showing evidence of investors’ interest in the market for the project) | Yes |
Relevant legal/regulatory provision (if any) | The Preparation Methodology outlines the analysis discussion of the micro-economic environment where the PPP project is ... More |
Is there a specific methodology for the assessment? | Yes |
If yes, please elaborate | CPMA Order No 2015 / 8-221 on Aug. 24, 2015 MARKET INVESTIGATION AND PRIVATE PRIVATE PRINCIPAL INITIATIVE PROJECT COMMUN... More |
Is the assessment done in practice? | Yes |
Details: | It is a mandatory part of an investment project, and CPMA does not approve projects without such analysis. |
Environmental impact assessment | Yes |
Relevant legal/regulatory provision (if any) | Article 3 of Law on Environmental Impact Assessment for Planned Economic Activity No. I-1495 provides, "2. Environmental... More |
Is there a specific methodology for the assessment? | Yes |
If yes, please elaborate | The Manual for Environmental Impact Assessment in Lithuania http://www.am.lt/VI/en/VI/files/0.740565001014724261.pdf pro... More |
Is the assessment done in practice? | Yes |
Details: | This is in application of regulatory provisions and to better prepare PPP projects. |
Consultation process with affected communities on potential impact of the PPP project | Yes |
Relevant legal/regulatory provision (if any) | According to the Market Analysis Methodology, which CPVA follows, Chapter II provides: If the market research shows that... More |
Is there a specific methodology for the assessment? | Yes |
If yes, please elaborate | According to the Market Analysis Methodology, Chapter II provides: If the market research shows that the identified prob... More |
Is the assessment done in practice? | Yes |
Details: | It is a mandatory part of an investment project, and CPMA does not approve projects without such analysis. |
Does the procuring authority include the assessments (indicated in Question 12 above) in the request for proposals and/or tender documents (for example, as part of an Information Memorandum to the bidders)? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | According to Article 24.2 clause 3 and 8 of Public Procurement Law, the procedure of the suppliers qualification assessm... More |
and specify which of the assessments are included in the request for proposals and/or tender documents: | All assessments must be identified in advance based on the Public Procurement Law. |
Are the assessments published online? | No |
If yes, please provide the relevant legal/regulatory provisions (if any): | n/a |
specify the website | n/a |
please specify which of the assessments are published online: | n/a |
Does the procuring authority include a draft PPP contract in the request for proposals? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | Article 24(2)(9) of the Public Procurement Law stipulates, "[T]ender documents shall provide with contract conditions an... More |
If no, please elaborate | n/a |
Are the tender documents published online? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | Article 23.1 of the Public Procurement Law provides, "Notices (prior information notices, contract notices, contract awa... More |
and please specify the website: | https://pirkimai.eviesiejipirkimai.lt/login.asp?B=ppo and website of contracting authority (state or municipal authority... More |
In a case comparable to the case study assumptions, have standardized PPP model contracts and/or transaction documents been developed? | Yes |
If yes, please specify and provide a government- supported website where the mentioned standards are available or provide an electronic copy of them: | Refer to the Partnership Agreement as the model contract, available at http://www.ppplietuva.lt/teisine-metodine-informa... More |
In a case comparable to the case study assumptions, who is the responsible party for each of the following requirements? Obtaining the required urban permits: Procuring authority (or other Government entity) | No |
Private Partner | No |
Private partner with facilitation role assigned to the procuring authority (or other Government entity) | No |
To be established in the contract | Yes |
Relevant legal/regulatory provision (if any) | According to Article 13.4 of the Partnership Agreement, "On request of the Private entity or the Investor, the Public en... More |
Obtaining the required environmental permits: Procuring authority (or other Government entity) | No |
Private Partner | No |
Private partner with facilitation role assigned to the procuring authority (or other Government entity) | No |
To be established in the contract | Yes |
Relevant legal/regulatory provision (if any) | According to Article 13.4 of the Partnership Agreement, "On request of the Private entity or the Investor, the Public en... More |
Obtaining the required operational permits: Procuring authority (or other Government entity) | No |
Private Partner | No |
Private partner with facilitation role assigned to the procuring authority (or other Government entity) | No |
To be established in the contract | Yes |
Relevant legal/regulatory provision (if any) | According to Article 13.4 of the Partnership Agreement, "On request of the Private entity or the Investor, the Public en... More |
Obtaining the required land: Procuring authority (or other Government entity) | Yes |
Private Partner | No |
Private partner with facilitation role assigned to the procuring authority (or other Government entity) | No |
To be established in the contract | No |
Relevant legal/regulatory provision (if any) | According to Art. 151(1) of the Investments Law provides, "Under a general government and private entities’ partnership ... More |
Obtaining the required right of way: Procuring authority (or other Government entity) | Yes |
Private Partner | No |
Private partner with facilitation role assigned to the procuring authority (or other Government entity) | No |
To be established in the contract | No |
Relevant legal/regulatory provision (if any) | In case of making available land, as previously mentioned, the right of way would be included. In other cases related to... More |
Question | Answer |
---|---|
Which of the following options best describes the required qualifications of the bid evaluation committee members? (Please select only one): The membership of the bid evaluation committee is specified and/or its members are required to meet detailed quali | No |
If yes, please provide the relevant legal/regulatory provisions (if any): | No |
The bid evaluation committee members require sufficient qualification without specific details. | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | Article 16(2) of the Public Procurement Law stipulates that members of the Procurement Commission would be appointed tak... More |
The bid evaluation committee members are not required to have any specific qualifications. | No |
Please elaborate and provide examples: | n/a |
Does the procuring authority issue a public procurement notice of the PPP project? | Yes |
If yes, please specify the means of publication and provide the relevant legal/regulatory provisions (if any): | Article 22(1) of the Public Procurement Law provides that procurement notice shall be published for any public tender (e... More |
If yes, is the public procurement notice published online? | Yes |
If yes, please specify the website: | https://pirkimai.eviesiejipirkimai.lt/login.asp?B=ppo; also on http://ted.europa.eu/TED/main/HomePage.do |
Are foreign companies prohibited from participating in the bidding process? | No |
If yes, please provide the relevant legal/regulatory provisions (if any): | n/a |
In a case comparable to the case study assumptions, does the procuring authority grant the potential bidders a minimum period of time to submit their bids? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | According to the Article 28 of the Public Procurement Law, the procuring authority must fix a sufficient time limit for ... More |
and the time in calendar days: | 52 |
Open tendering: Available | Yes |
Default | No |
Relevant legal/regulatory provision (if any) | According to Article 43.1 of the Public Procurement, "The number of tenderers in the open procedure shall be unlimited. ... More |
Restricted tendering (with pre-qualification stage): Available | Yes |
Default | No |
Relevant legal/regulatory provision (if any) | According to Article 45 of the Public Procurement Law: 1. The contracting authority shall conduct the restricted procedu... More |
Multi-stage tendering (with shortlisting of final candidate(s)): Available | Yes |
Default | No |
Relevant legal/regulatory provision (if any) | According to Article 45 of the Public Procurement Law: 1. The contracting authority shall conduct the restricted procedu... More |
Competitive dialogue: Available | Yes |
Default | No |
Relevant legal/regulatory provision (if any) | According to Article 50 of the Public Procurement Law: 1. Where the contracting authority considers that the use of the ... More |
Direct negotiation with more than one candidate: Available | No |
Default | No |
Relevant legal/regulatory provision (if any) | n/a |
Direct negotiation with only one candidate: Available | No |
Default | No |
Relevant legal/regulatory provision (if any) | n/a |
Other. Specify: | No |
Available | No |
Default | No |
Relevant legal/regulatory provision (if any) | n/a |
Do the tender documents detail the procedure of the procurement process providing the same information to all the bidders? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | Article 24 of the Public Procurement Law establishes that "In contract documents the contracting authority shall give co... More |
If no, please elaborate: | n/a |
Do the tender documents specify the prequalification/shortlisting criteria (when applicable) in order to make them available to all the bidders? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | Article 47.4 of the Public Procurement Law states, "when selecting candidates, the contracting authority shall apply onl... More |
Based on your experience, is it always the case that the specified criteria are respected in practice? | Yes |
If yes, please specify and provide the relevant legal/regulatory provisions (if any): | Article 3(1) of the Procurement Law sets that procurement procedures shall comply with principles of transparency, non-d... More |
If no, please elaborate: | n/a |
Can interested parties/potential bidders submit questions to clarify the public procurement notice and/or the request for proposals? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | Article 27 of the Public Procurement Law provides the rules on how and when the procuring authority should respond to th... More |
If yes, notwithstanding confidential information pertaining to the bidders, does the procuring authority disclose those questions and clarifications to all potential bidders? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | Article 27(3) of the Public Procurement Law provides, '[The] contracting authority, when submitting a response to the te... More |
Based on your experience, is it always the case that this disclosure of information is done in practice? | Yes |
If yes, please specify: | Contributors confirmed that this disclosure was always followed in practice and infringing such disclosure could result ... More |
If no, please elaborate: | n/a |
Besides questions and clarifications, can the procuring authority conduct pre-bidding conference? | Yes |
If yes, please specify and provide the relevant legal/regulatory provisions (if any): | According to Article 27 of Public Procurement Law before the expiry of the time limit for the submission of tenders, the... More |
If yes, notwithstanding confidential information pertaining to the bidders, does the procuring authority disclose the content and the results of the pre-bid conference to all bidders? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | Article 27(6) of Public Procurement Law provides that the procuring authority shall prepare minutes of the meeting (conf... More |
Based on your experience, is it always the case that this disclosure of information is done in practice? | Yes |
If yes, please specify: | Contributors provided that in all cases all bidders received the same information. |
If no, please elaborate: | n/a |
In a case comparable to the case study assumptions, does the procuring authority require the bidders to prepare and present a financial model with their proposals? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | The CPMA Methodological Documents include the Standard PPP Contract (Annex 5) (Partnership Agreement). In Section II on ... More |
If no, please elaborate: | n/a |
Does the procuring authority evaluate the proposals strictly and solely in accordance with the evaluation criteria stated in the tender documents? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | Article 32 of the Public Procurement Law provides the rules on how the procuring authority has to evaluate the proposals... More |
Evaluation criteria is not set in the tender documents | No |
In the case where only one proposal is submitted (sole proposals), which of the following options best describes the way the procuring authority deals with them? (Please select only one)?: The procuring authority follows a specific procedure before awardi | No |
Please specify and provide the relevant legal/regulatory provisions (if any): | n/a |
The procuring authority considers sole proposals valid as long as they meet the conditions outlined in the tender documents. | Yes |
Please provide the relevant legal/regulatory provisions (if any): | Article 39 of Public Procurement Law provides the procedures that the procuring authority must follow when only one prop... More |
The procuring authority does not award a PPP contract if only one proposal is submitted. | No |
Please provide the relevant legal/regulatory provisions (if any): | n/a |
The regulatory framework does not include any provisions. | No |
Does the procuring authority publish the award notice? | Yes |
If yes, please specify the means of publication and provide the relevant legal/regulatory provisions (if any): | According to Article 23 of the Public Procurement Law, "notices (prior information notices, contract notices, contract ... More |
If yes, is the public procurement award notice published online? | Yes |
If yes, please specify the website: | https://pirkimai.eviesiejipirkimai.lt/login.asp?B=ppo; http://ted.europa.eu/TED/main/HomePage.do |
Does the procuring authority provide all the bidders with the result of the PPP procurement process? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | Article 41 of the Public Procurement Law provides, "the contracting authority shall as soon as possible, but not later t... More |
If no, please elaborate: | n/a |
If yes, does the notification of the result of the PPP procurement process include the grounds for the selection of the winning bid? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | Article 41(1) of the Public Procurement Law sets a requirement to provide all bidders who have submitted proposals to di... More |
Is there a standstill (or pause) period after the contract award and before the signing of the contract in order to allow unsuccessful bidders to challenge the award decision? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | According to Article 94 of the Public Procurement Law: 1. A supplier shall have the right to file a claim with the contr... More |
and the time in calendar days: | 15 |
Is the standstill period set out in the notice of intention to award? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | Contributors confirmed that the dispatch to suppliers of a written notice of the contracting authority of the decision a... More |
Does the regulatory framework restrict negotiations with the selected bidder between the award and the signature of the PPP contract in order to prevent an unfair disadvantage to the other bidders? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | Article 18(3) of the Public Procurement Law prohibits negotiations with the selected bidders or any alterations after th... More |
Based on your experience, is it always the case that this restriction is respected in practice? | Yes |
If yes, please specify: | Contributors confirmed that this restriction is always respected and that the infringement of imperative requirements of... More |
If no, please elaborate: | n/a |
Does the procuring authority publish the PPP contract? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | Article 18(11) of the Public Procurement Law imposes an obligation on contracting authorities to publish the successful ... More |
If yes, which of the following options best describes this publication (choose only one)?: Publication of the full PPP contract including all its annexes and appendixes | No |
Publication of the full PPP contract without including all its annexes and appendixes | Yes |
Publication of a summary of the PPP contract without publishing the full PPP contract | No |
Publication of a summary of the PPP contract along with the full PPP contract including all its annexes and appendixes | |
Publication of a summary of the PPP contract along with the full PPP contract without including all its annexes and appendixes | No |
If yes, is it published online? | Yes |
If yes, please specify the website: | https://www.cvpp.lt/ |
If yes, does the procuring authority also publish any subsequent amendment made to the PPP contract? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | Article 18(11) of the Public Procurement Law imposes an obligation on contracting authorities to publish the successful ... More |
Question | Answer |
---|---|
Has the procuring or contract management authority established a system to manage the implementation of the PPP contract (e.g. attributing responsibilities or establishing specific management tools)? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | The Partnership Agreement provides for establishing a monitoring and evaluation system in each individual contract (Chap... More |
If yes, which of the following tools does it include (check all that apply)?: Establishment of a PPP contract management team | Yes |
Relevant legal/regulatory provisions (if any): | Sections 1.2. and 1.4. of PPP Projects Implementation and Management Guidelines (PPP implementation Guidelines) (Lithuan... More |
Participation of the members of the PPP contract management team in the PPP procurement process and/or vice versa | Yes |
Relevant legal/regulatory provisions (if any): | Section 1.3.1 of the PPP Implementation Guidelines provide that the PPP contract management framework shall start to for... More |
Elaboration of a PPP implementation manual or an equivalent document | Yes |
Relevant legal/regulatory provisions (if any): | Section 1.1 Table 1 of the PPP Implementation Guidelines provides that the contract management teams shall be authorized... More |
Establishment of personnel training programs (i.e. initial training and continued training throughout the course of the project) | No |
Relevant legal/regulatory provisions (if any): | n/a |
Establishment of a risk mitigation mechanism which considers the evolving nature of risks throughout the project lifecycle (guidelines, specific processes, insurance regime, etc.) | Yes |
Relevant legal/regulatory provisions (if any): | Section 3.6 of the PPP implementation Guidelines provides, "Insufficient Risks should be monitored continuously througho... More |
Which of the following options best describes the required qualifications of the PPP contract management team members? (Please select only one): The membership of the PPP contract management team is specified and/or its members are required to meet detail | No |
If yes, please specify and provide the relevant legal/regulatory provisions (if any): | n/a |
The PPP contract management team members are required to meet sufficient qualification without specific details. | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | Sections 1.2. and 1.4. of the PPP implementation Guidelines generally provides that such team shall consist of a PPP pro... More |
The PPP contract management team members are not required to meet any specific qualifications. | No |
Please elaborate and provide examples: | n/a |
Does the procuring or contract management authority establish a system for tracking progress and completion of construction works under a PPP contract? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | Chapter X (Articles 27-29) of the Partnership Agreement regulates the "Control of Performance Obligations" and gives the... More |
If yes, is the PPP contract construction performance information made available to the public? | No |
If yes, please provide the relevant legal/regulatory provisions (if any): | n/a |
If yes, is the PPP contract construction performance information made publicly available online? | n/a |
If yes, please specify the website: | n/a |
Does the procuring or contract management authority establish a monitoring and evaluation system of the PPP contract implementation after construction? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | The Partnership Agreement provides for establishing a monitoring and evaluation system in each individual contract (Chap... More |
If yes, which of the following tools does it include (check all that apply)?: Performance is assessed against evaluation criteria set in the tender documents and the PPP contract | Yes |
Relevant legal/regulatory provisions (if any) | The Partnership Agreement Annex 2 would embody technical specifications and penalties for not abiding by the set evaluat... More |
The procuring or contract management authority can abate (reduce) payments for non-performance of operating obligations under the PPP contract | Yes |
Relevant legal/regulatory provisions (if any) | Article 24.5 of the Partnership Agreement provides, "Any taxes, levies or other payments of any nature shall not be dedu... More |
The private partner must provide the procuring or contract management authority with periodic operational and financial data | Yes |
Relevant legal/regulatory provisions (if any) | Chapter X (Article 28.1) of the Partnership Agreement under "Control of Performance of Obligations" provides, "[T]he Pri... More |
The procuring or contract management authority must periodically gather information on the performance of the PPP contract | Yes |
Relevant legal/regulatory provisions (if any) | Article 28.1. of the Partnership Agreement provides, "The Private Entity shall provide the Public Entity information and... More |
The PPP contract performance information must be available to the public | No |
Relevant legal/regulatory provisions (if any) | n/a |
Is PPP contract performance information made publicly available online? | No |
If yes, please specify the website: | n/a |
Are foreign companies prohibited from repatriating the income resulting from the operation of a PPP project? | No |
If yes, please provide the relevant legal/regulatory provisions (if any): | n/a |
Does the regulatory framework (including standard contractual clauses) expressly regulate changes in the ownership structure (i.e. stakeholder composition) of the private partner and/or assignment of the PPP contract? | Yes |
If yes, please provide the relevant legal/regulatory/standard contractual provisions (if any): | Partnership Agreement Chapter XI on "Transfer of Rights and Obligations" Article 30.2. provides, "The Private Entity sha... More |
If yes, which of the following circumstances are specifically regulated? (check all that apply): Any change in the private partner during an initial period (e.g. construction and first five years of operation). | No |
If yes, please provide the relevant legal/regulatory/standard contractual provisions (if any): | n/a |
Changes of ownership/contract assignment, at any time during the contract, must preserve the same technical qualifications as the original operator. | Yes |
If yes, please provide the relevant legal/regulatory/standard contractual provisions (if any): | Article 30.3 of the Partnership Agreement provides, "Apart from the cases set forth in paragraph 32.2 and paragraph 34.2... More |
In other cases, flexibility to change the ownership structure and/or assign the contract. | No |
If yes, please provide the relevant legal/regulatory/standard contractual provisions (if any): | n/a |
Does the regulatory framework (including standard contractual clauses) expressly regulate the modification or renegotiation of the PPP contract (once the contract is signed)? | Yes |
If yes, please provide the relevant legal/regulatory/standard contractual provisions (if any): | The Partnership Agreement in Article 39.1 ensures the possibility of modifying the contract "provided that such amendmen... More |
If yes, is an approval from a government authority, other than the procuring authority, required? | No |
If yes, please provide the relevant legal/regulatory/standard contractual provisions (if any): | n/a |
If yes to question 46, which of the following circumstances are specifically regulated? (check all that apply): A change in the scope and/or object of the contract. | Yes |
If yes, please provide the relevant legal/regulatory/standard contractual provisions (if any): | Article 39.2.1 of the Partnership Agreement permits such a change provided the conditions specified in Article 40 of thi... More |
A change in the risk allocation of the contract. | No |
If yes, please provide the relevant legal/regulatory/standard contractual provisions (if any): | n/a |
A change in the financial and/or economic balance of the contract. | Yes |
If yes, please provide the relevant legal/regulatory/standard contractual provisions (if any): | No regulatory basis |
A change in the duration of the contract. | No |
If yes, please provide the relevant legal/regulatory/standard contractual provisions (if any): | n/a |
A change in the agreed price or tariff. | Yes |
If yes, please provide the relevant legal/regulatory/standard contractual provisions (if any): | Articles 39.2.2. and 39.2.3. of the Partnership Agreement provide, "39.2.2. if the value of specific Agreement amendment... More |
Can the procuring authority unilaterally modify a PPP contract? | No |
If yes, please provide the relevant legal/regulatory/standard contractual provisions (if any): | n/a |
Does the regulatory framework (including standard contractual clauses) expressly regulate the following circumstances that may occur during the life of the PPP contract? (check all that apply): Force Majeure | Yes |
If yes, please provide the relevant legal/regulatory/standard contractual provisions (if any): | Articles 43, 44, 47 of the Partnership Agreement apply. Article 44.2 of the Partnership Agreement provides, "The Parties... More |
Material Adverse government action . | No |
If yes, please provide the relevant legal/regulatory/standard contractual provisions (if any): | n/a |
Change in the Law. | Yes |
If yes, please provide the relevant legal/regulatory/standard contractual provisions (if any): | Article 42.2.6 of the Partnership Agreement details one of the substantial violations as, "[I]f the requirements of the ... More |
Refinancing. | Yes |
If yes, please provide the relevant legal/regulatory/standard contractual provisions (if any): | Section IX of the Partnership Agreement on "Payments," precisely Article 26, provides, "26.1. The Private Entity shall h... More |
Subcontracting and replacement of the subcontractors. | Yes |
If yes, please provide the relevant legal/regulatory/standard contractual provisions (if any): | Article 20 of the Partnership Agreement provides, "20.1. The Private entity, at its own expense (i.e. not increasing th... More |
Does the regulatory framework (including standard contractual clauses) allow for administrative and/or contractual complaint review mechanisms to address disputes arising from the implementation of PPP contracts? | Yes |
If yes, please specify and provide the relevant legal/regulatory/standard contractual provisions (if any): | When a foreign investor is concerned, Article 6 of the Investments Law would apply. This Article provides, "2. Disputes... More |
If yes, please specify which of the following options are available (check all that apply): Local administrative review body | No |
If yes, please specify: | n/a |
Local courts | Yes |
Domestic arbitration | Yes |
International arbitration | Yes |
Investor-State Dispute Settlement (ISDS) | Yes |
Mediation | Yes |
Please provide the relevant legal/ regulatory/standard contractual provisions (if any) | When a foreign investor is concerned, Article 6 of the Investments Law would apply. This Article provides, "2. Disputes... More |
If applicable, are arbitration awards enforceable by the local courts?: Domestic Arbitration | Yes |
If yes, please provide the relevant legal/ regulatory provisions/standard contractual provisions (if any): | Article 22(2) of the Civil Procedures Code provides, "2. Courts also hear cases in accordance with extraordinary legal p... More |
International arbitration | Yes |
If yes, please provide the relevant legal/ regulatory provisions/standard contractual provisions (if any): | Article 26 of the Law on Commercial Arbitration provides, "1. An arbitral award or ruling on interim measures made in an... More |
Investor-State arbitration | Yes |
If yes, please provide the relevant legal/ regulatory provisions/standard contractual provisions (if any): | Article 6.3 of the Investment Law provides that Investment disputes shall also be settled with due regard to the provisi... More |
Does the regulatory framework (including standard contractual clauses) allow for the restructuring of a PPP private partner (SPV) in financial difficulty prior to insolvency? | No |
If yes, please specify and provide the relevant legal/regulatory/standard contractual provisions (if any): | n/a |
Does the regulatory framework (including standard contractual clauses) allow for the lenders to take control of the PPP project (lender step-in rights) if either the private partner defaults or if the PPP contract is under threat of termination for failur | Yes |
If yes, please provide the relevant legal/regulatory/standard contractual provisions (if any): | Article 32 of the Partnership Agreement provides, "32.2. In case of the Private Entity's failure to perform or improper ... More |
If yes, which of the following options best describes the lender step-in right? (Please select only one): The regulatory framework expressly regulates the lender step-in rights. | No |
If yes, please specify and provide the relevant legal/regulatory/standard contractual provisions (if any): | n/a |
The regulatory framework prescribes that a direct agreement should be signed with the lenders. | Yes |
If yes, please specify and provide the relevant legal/regulatory/standard contractual provisions (if any): | Article 32 of the Partnership Agreement provides, "32.1. The Funder shall be entitled to use a step-in right, set forth... More |
The regulatory framework prescribes that the lender step-in rights should be regulated in the contract. | No |
If yes, please specify and provide the relevant legal/regulatory/standard contractual provisions (if any): | n/a |
Other. | No |
Please Specify: | n/a |
Does the regulatory framework (including standard contractual clauses) expressly establish the grounds for termination of a PPP contract? | Yes |
If yes, please specify and provide the relevant legal/regulatory/standard contractual provisions (if any): | The grounds would include, the termination of the contract determined by the circumstances which depend on the private e... More |
If yes, does the regulatory framework (including standard contractual clauses) establish the consequences for the termination of the PPP contract? | Yes |
If yes, please specify and provide the relevant legal/regulatory/standard contractual provisions (if any): | Articles 45-48 of the Partnership Agreement apply. Article 45.1. of the Partnership Agreement provides, "If the Agreemen... More |
Question | Answer |
---|---|
Are unsolicited proposals in [country_name]: (choose only one): Explicitly prohibited by the legal framework? (If prohibited, skip to section F) | No |
Explicitly allowed by the legal framework? | Yes |
Not regulated by the legal framework, but do happen in practice? | No |
Not regulated by the legal framework, and do not happen in practice? (if not done in practice, skip to section F) | No |
If the legal framework explicitly prohibits or allows unsolicited proposals, please provide the relevant legal/regulatory provisions | Article 13 of the Investments Law allows the submission of unsolicited proposals. And Art. 4 of the PPP Resolution as am... More |
Does the procuring authority conduct an assessment to evaluate unsolicited proposals? (if not, skip to question 37) | Yes |
If yes, please specify and provide the relevant legal/regulatory provisions (if any | Amended Article 4 of the PPP Resolution provides the basis for unsolicited proposals but refers to the general rules of ... More |
If yes, is there any vetting procedure and/or pre-feasibility analysis before fully assessing the unsolicited proposal? | No |
If yes, please provide the relevant legal/regulatory provisions (if any): | n/a |
Which of the following options best describe how the procuring authority ensures that unsolicited proposals are consistent with existing government priorities? (Please select only one): The procuring authority follows a specific procedure to ensure the co | No |
If yes, please specify and provide the relevant legal/regulatory provisions (if any): | n/a |
The regulatory framework requires unsolicited proposals to be among the existing government priorities without establishing specific procedures to achieve that goal. | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | According to Article 4 of the PPP Resolution, unsolicited proposals are implemented in accordance with the requirements,... More |
The procuring authority does not evaluate unsolicited proposals against existing government priorities. | No |
Please elaborate and provide examples: | n/a |
Does the procuring authority initiate a competitive PPP procurement procedure when proceeding with the unsolicited proposal? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | Amended Article 4 of the PPP Resolution refers to the application of the general rules on PPP procurement with regards t... More |
Does the procuring authority grant a minimum period of time to additional prospective bidders (besides the proponent) to prepare their proposals? | Yes |
If yes, please provide the relevant legal/regulatory provisions (if any): | The general rules on procuring PPPs would apply according to amended Article 4 of the PPP Resolution. |
and the time in calendar days: | 52 |
Does the procuring authority use any of the following incentive mechanisms to reward/compensate the presentation of unsolicited proposals? (check all that apply): Access to the best and final offer (BAFO) process and/or automatic shortlisting. | No |
Developer’s fee (reimbursing the original proponent for the project development cost). | No |
Bid Bonus. | No |
Swiss challenge (If unsuccessful, the original proponent has the option to match the winning bid and win the contract). | No |
Other. | No |
Please specify: | n/a |
Please provide the relevant legal/regulatory provisions (if any): | n/a |